Preliminaries in Construction: The Complete UK Guide

By

Last Updated May 15, 2025

By
Two men on a construction jobsite wearing safety gear review data on a tablet.

Preliminaries often called “prelims,” “general conditions,” or “non-physical costs” - are the costs and requirements necessary to complete a construction project but are not tied to any specific work section. They encompass essential overheads such as site management, temporary works, health and safety measures, and regulatory compliance. In the UK, these are frequently referenced via the NBS (National Building Specification) classification system and integrated into JCT contracts as a separate section.

Table of contents

Importance and UK Context

All costs in a construction tender or contract will fall into one of two categories:

  • Costs arising from specific work sections (direct costs).
  • Costs required for the entire project (indirect costs, also referred to as preliminaries or general conditions).

Preliminaries describe the essential conditions and resources - beyond direct labour and materials - needed to ensure project-wide efficiency, safety, and regulatory compliance. They can be one-time or ongoing costs. In the UK, contractors often rely on JCT contracts (Joint Contracts Tribunal) to structure these prelims clearly, using standards like the NBS to streamline classification.

Why Preliminaries Matter for UK Contractors

  • Transparent Tendering: By listing prelims separately, owners and contractors gain clearer visibility over which costs are tied to running the project as a whole.
  • Clearer Project Scope: Prelims ensure that everyone - from project managers to site engineers - has a defined boundary of responsibilities and budget allocations.
  • Enhanced Planning & Risk Management: Accurate prelims help contractors plan site access, environmental measures, and regulatory compliance before work begins, reducing unexpected overruns.
  • Regulatory Compliance: The UK’s building regulations and safety standards can be strict; preliminaries account for onsite health and safety, environmental requirements, and any legal obligations.

Common Project Preliminaries

1. Management & Administration

These costs include payments to project managers, site managers, and other administrative staff who oversee the entire project rather than specific tasks. Listing these as preliminaries ensures transparency for both owners and contractors, clearly separating overheads from direct costs.

2. Site-Based Services

From access roads to site offices, temporary utilities, cleaning, waste disposal, and environmental controls, many services support overall site operations. This category also covers security measures and mitigating any disturbance to neighbours or adjacent structures.

3. Temporary Works

Temporary works - such as scaffolding, fencing, frameworks, and shoring - ensure safe and efficient construction environments. Though essential to the building process, they’re not part of the finished structure, making them a clear prelims item.

4. Mockups, Testing & Sampling

Designers and owners often require mockups to verify how finishes will appear. Typical testing and sampling procedures include concrete slump tests or lumber moisture checks, ensuring materials meet full-project standards. These costs are generally spread across the entire project rather than applied to a single work section.

5. Health & Safety & Environmental Compliance

Preliminaries must include PPE, site safety signage, first-aid facilities, environmental mitigations (e.g., erosion protection), and any UK-specific compliance measures. These ongoing costs protect workers, the environment, and satisfy construction regulations.

6. Other Project-Wide Costs

This category covers items like transport to and from the site, site-wide technology, administrative fees, and other overhead not attributable to a single task. Including them ensures no hidden costs absorb a contractor’s contingency.

Learn about the Future of the Built Environment - Read Procore's Future State of Construction Report

Learn how contractors, subcontractors, and project teams can take advantage of new opportunities to boost efficiency and profitability over the next decade.

Download the report to get your roadmap to the future state of construction.

Download Now

Construction Preliminaries Examples & Templates

When specifying preliminaries, contracts often reference NBS numbering or JCT contract structures. However, contractors may also use an ad hoc numbering system and text to fit the situation.

Here are two examples of preliminaries from projects in Australia and the UK:

A typical construction preliminaries template will include preliminaries for common aspects of a contract, including: 

  • 00-05-10 Project Definition 
  • 00-05-15 Works Terminology
  • 00-05-20 Project Participants 
  • 00-05-70 Project Location
  • 00-10-70 Works Contract 
  • 00-30-70 Works Contract Procurement
  • 00-40-70 Works Contract Establishment
  • 00-50-70 Works Contract Management
  • 00-60-70 Works Contract Verification 
  • 00-70-70 Works Contract Administration 
  • 00-80-70 Works Contract Completion

Cost Allocation and Pricing for Preliminaries

Accurate estimating of preliminaries is critical for overall budgeting. In the UK, prelims can be priced in these main ways:

  • Lump Sum: A single figure covering all overheads.
  • Percentage of Contract Value: Usually 5%–15%, depending on the project’s scale, complexity, location, and duration.

A thorough, transparent breakdown helps prevent disputes, ensuring both contractor and owner understand the financial obligations inherent in running the project site.

Construction Contract Preliminaries vs. Preambles

The construction preliminaries breakdown - along with the work sections (activities and tasks) - should fully describe all that’s required to complete the project.

By contrast, the preamble registers the parties to the contract, summarises negotiations and tender procedures, and clarifies project objectives and standards. While the preamble sets the contract context, preliminaries detail the general conditions and site-wide requirements.

Final Thoughts

In UK construction, preliminaries (or prelims, general conditions) are non-physical costs that enable the smooth and compliant execution of a project. They include everything from administrative overheads and site-based services to temporary works and testing & sampling. Accurately pricing these items - often amounting to 5–15% of the total contract - supports transparent tendering, improves project planning, and helps mitigate risks.

Categories:

Preconstruction, Project Management, Safety and Compliance

Tags:

Written by

Tom Noctor

16 articles

Having worked in construction for many years both on the ground as an electrician and in the design space in roles such as BIM Manager, I witnessed the highly inefficient operations of our industry and also the amount of waste generated from project delivery. I am a Digital Construction Technologies advocate @Procore Technologies, supporting and guiding the construction industry in adopting/utilising technology to deliver projects in a lean sustainable manner.

View profile

Explore more helpful resources

article-image

AI in Construction and the Built Environment

Artificial intelligence (AI) will transform UK construction and how we assess and interact with our built environment, bringing new efficiencies and insights once difficult to imagine. AI technologies now embed...

article-image

How Construction Companies Can Drive Value from Automation

Most of us use automation in our day-to-day lives, even if we might not realise it. Robot vacuum cleaners, email scheduling tools, contactless payments and navigation apps are all examples...

article-image

How Construction Project Management Drives Project Success

Construction is widely acknowledged as one of the most complex and rapidly evolving industries in the world. Beyond bricks and mortar, it calls for precision planning, close coordination, and expert...

article-image

From Plan to Site: Why Construction Submittals Matter

In construction, getting all the details right matters, particularly when it comes to materials, equipment, and the methods used to bring a project to life. Construction submittals are key to...

Procore is committed to advancing the construction industry by improving the lives of people working in construction, driving technology innovation, and building a global community of groundbreakers. Our connected global construction platform unites all stakeholders on a project with unlimited access to support and a business model designed for the construction industry.

LinkedIn Icon
LinkedIn
Facebook icon
Facebook
Twitter icon
Twitter
Instagram Icon
Instagram
YouTube icon
YouTube

Call us at (+44) 0800 368 7703 to speak with a product expert.

Apple LogoApple App StoreGoogle Play logoGoogle Play

Downloads

Apple LogoApple App StoreGoogle Play logoGoogle Play
  • Privacy Notice
  • Terms of Service

© 2025 Procore Technologies, Inc.